01
Analyse
Map how each team really worked in the old tool: structures, habits, and the templates worth keeping.
Case study · B2B services company, name withheld
Moving a whole company from one work-management tool to another, mid-flight, with live client projects running. How it was analysed, built and rolled out, and what it changed far beyond the delivery team.
27
people moved, across every team
≈ 6 wks
from decision to full cutover
≈ 36%
lower tool cost
0
deal or data lost on the way
01 — Diagnosis
The existing tool was fine for steering, less so for day-to-day operations. Before choosing anything, I listed what the business actually needed, team by team.
Formulas inside the columns, instead of numbers living in side spreadsheets.
Gantt views to see load and delivery dates ahead of time.
A native link between the CRM, the chat and finance.
Hours logged on the task itself, not rebuilt afterwards.
Around 36% cheaper for the whole company.
02 — Approach
About six weeks, four steps. The rule: nobody moves until the new setup is at least as good as the old one, and already better where it counts.
01
Map how each team really worked in the old tool: structures, habits, and the templates worth keeping.
02
Recreate equivalent structures, and improve them before anyone moves. Templates built from the teams’ own methods, to gain speed from day one.
03
A champion, fluent in the old tool and technically curious, takes over governance. Side-by-side comparison slides, and small build challenges to learn by doing.
04
Every live project migrated, old ones archived with their history. Automations rebuilt, new workflows and integrations added (Slack, Google scripts).
The risky part // client side
One client had a live project and still had playbooks, data and templates to hand over. Had they kept uploading into the old tool, we would have lost data, or lost face.
The answer was a clean cutover and clear communication, so the client always knew where to send things, and nothing kept landing in the old tool.
Result → no data lost, and no awkward moment with the client.
03 — Outcome
The biggest gain was not for the consultants. It was the link between teams: a signed quote now creates the project, and a finished project triggers the invoice.
CRM
HubSpot
WORK
monday.com
FINANCE
Pennylane
BOOKS
Accounting
Projects are easier to run, with one way of doing things.
Everyone sees the same information, and shares it more easily.
Better forecasting gave the teams real velocity.
The load of each stage could finally be measured and adjusted.
The move surfaced optimisations and automations nobody had seen.
Sales, delivery and finance now work on one continuous flow.
04 — What I keep from it